Testing

Before dispatch, each APT transformer undergoes all routine tests according to relevant standard specifications. Test as follows as per IS1180

Tests Performed

  • Ratio test at all taps
  • Measurement of no-load loss and current at rated voltage and frequency
  • Measurement of load loss and impedance volts at rated current
  • Induced over-voltage test Separate source voltage withstand test
  • Winding resistance (HV&LV)
  • Insulation resistance

Additional Tests

If requested by the buyer, the following tests can
also be carried out at an additional cost.

  • Temperature rise test
  • Impulse test for lighting